单选题A technician(技术) has a current baseline(基准线) and is told to install additional(添加) memory and a faster NIC card. At which point in time should the next baseline be run?()A After the memory is installedB Before the upgrade is performedC After the NIC is installedD After the upgrades are performed
单选题
A technician(技术) has a current baseline(基准线) and is told to install additional(添加) memory and a faster NIC card. At which point in time should the next baseline be run?()
A
After the memory is installed
B
Before the upgrade is performed
C
After the NIC is installed
D
After the upgrades are performed
参考解析
解析:
暂无解析
相关考题:
During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:A.Now becomes the new schedule, including the changes, and the original baseline is disregarded.B.Is still the original baseline but annotated to reflect that a change has taken place.C.Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.D.Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)E.Is the same since baseline schedules cannot change once the development phase is completed.
156 During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:A. Now becomes the new schedule, including the changes, and the original baseline is disregarded. B. Is still the original baseline but annotated to reflect that a change has taken place.C. Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.D. Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)E. Is the same since baseline schedules cannot change once the development phase is completed
He told me that he ____ in Naples the previous year.A、has been workingB、has workedC、had been workingD、had been worked
A technician wants to compare a new server performance over a period of time. Which of the following should the technician do FIRST?() A. Monitor processor performance logsB. Constantly check the task managerC. Use performance server logsD. Establish a baseline for the server
The manager __________the workers how to improve the program since 9 a.m.A.has toldB.is tellingC.has been tellingD.will have told
The technician has suspicions that a browser has been hijacked. Which of the following should the technician look for in this situation?()A、A new default gateway has been setup.B、A new Internet shortcut has been added.C、A new web browser has been installed and is now the default.D、A proxy server has been enabled.
A technician receives a boot error message OS not found. Which of the following should thetechnician check? ()A、The boot order in the BIOSB、If Plug and Play is enabledC、If the computer is in Safe ModeD、If the BIOS is current
A technician is building a Windows 2008 server and has installed a motherboard, processor, and power supply. Which of the following optical drives should the technician install?()A、Flash DriveB、DVD-RWC、CD-ROMD、SSD
A technician wants to compare a new server performance over a period of time. Which of the following should the technician do FIRST?()A、Monitor processor performance logsB、Constantly check the task managerC、Use performance server logsD、Establish a baseline for the server
After a baseline check was completed it was noted that the network was working far below the level of the last baseline. Which of the following should the technician do NEXT to determine where the network problems are occurring?()A、Upgrade the firmware on all routers and switchesB、Reboot the entire network one device at a timeC、Conduct a network traffic analysisD、Rerun the baseline to ensure the results were correct
A technician(技术) has a current baseline(基准线) and is told to install additional(添加) memory and a faster NIC card. At which point in time should the next baseline be run?()A、 After the memory is installedB、 Before the upgrade is performedC、 After the NIC is installedD、 After the upgrades are performed
A technician has been given a task to create a separate location for disaster recovery. Thecompany has very high uptime requirements and will lose money if there is any downtime. Whichof the following deployments should the technician consider?()A、Hot siteB、Warm siteC、Fault tolerant siteD、Cold site
A server technician has been attempting to install an operating system on the company test server for several days. The technician has experienced error messages at several points of theinstallation and the system has frozen during various parts of the boot process. The technician has replaced the power supply, graphics card and installation disk with known good components.Which of the following could be causing these issues?()A、Storage driver not loadedB、Fragmented hard driveC、Damaged or faulty NIC chipsetD、Damaged or faulty system boardE、Memory incompatible with the processorF、Missing voltage regulator
A client has called with concerns that their computer problem has not been resolved by the onsite technician who has left. As the technicians supervisor, which of the following is the BEST course of action in this situation?()A、Tell the client that they will need to place another service call.B、Ask the client if they would like to discuss their computer problems in more detail.C、Tell the client that another technician will be sent out.D、Inform the client that the problem will be resolved by the onsite technician at another time.
An IBM technician specialist has a prospective customer who is excited about eX5 and is working on configuration for a very large complex opportunity. During the engagement the customer has changed the design several times and has significantly increased the scope. The customers recently selected a Business Partner who has been involved in the last few design changes. What steps should the IBM technician specialist take to make sure the customer is satisfied with the solution?()A、Turn over current design to Techline to create configurationsB、Perform knowledge transfer of design requirements to Business partner then disengageC、Work with Business Partner to engage Techline to assist with configuration and request technical and Delivery Assessment (TDA)D、Work with business partner to engage Techline to create configurations
单选题You have created a baseline metric, DISK_IO_BL, for the disk I/O metrics in your PROD database and you have been getting notifications whenever the database performance degrades. You optimize the database I/O to gain the performance and you decide to remove the baseline metrics. Which method would you use to remove the DISK_IO_BL baseline metrics?()AThe baseline, once created, cannot be removed.BDisable the baseline metrics in the Database Control Manage Metrics page.CThe baseline will be automatically removed once the database performance has been optimized.DDrop the baseline metrics by usingDBMS_WORKLOAD_REPOSITORY.DROP_BASELINE procedure.
单选题View the Exhibit that sets the threshold for the Current Open Cursors Count metric.Why is the Significance Level threshold type not available in the threshold setting?()A because AWR baseline is not enabledB because Current Open Cursors Count is not a basic metricC because the STATISTICS_LEVEL parameter is set to BASICD because the AWR baseline is a system-defined moving window baseline
单选题A technician works for a company that has recently been affected by a virus. The virus entered the network by using port 6000. Port 6000 is used by an application located on a server. The technician has been asked to block this port on all servers and computers except for the one server which uses this port. Which of the following should the technician do?()AUpdate the antivirus applicationBInstall critical update security patchesCAdjust the software firewall settingsDReplace the current antivirus program
单选题A technician has installed a new motherboard in a workstation, but after hardware tests, themotherboard has failed. Which of the following should the technician do FIRST before replacingthe motherboard? ()AReseat all power connections.BRemove the CMOS battery.CInstall the graphics card.DGround to the case.
单选题A technician has just finished installing a new server into a server rack. Which of the following should the technician do NEXT to complete the installation documentation?()AUpdate drivers, update operating system (e.g. Windows Update), create server baseline, createa new network diagram, update change management proceduresBCreate server baseline, label server, store vendor-specific documentation, update networkdiagrams, update asset tracking informationCCreate server baseline, assign server roles, install tape drive, delete network diagram, labelserver, update operating system (e.g. Windows Update)DInstall applications on server, install external drives, toss vendor-specific documentation,update network diagrams
单选题A technician wants to compare a new servers performance over a period of time. Which of the following should the technician do FIRST?()A Monitor processor performance logsB Constantly check the task managerC Use performance server logsD Establish a baseline for the server
单选题A technician has fixed a reported issue with a heavily used software program and users have verified that the program is working correctly. Which of the following should the technician do NEXT?()ADocument the process and update the baseline.BTest the theory of probable cause and verify with the software vendor.CEstablish a plan of action to be included in the business impact analysis.DImplement the software manufacturer workaround.
单选题A technician is building a Windows 2008 server and has installed a motherboard, processor, and power supply. Which of the following optical drives should the technician install?()AFlash DriveBDVD-RWCCD-ROMDSSD
多选题A server technician has been attempting to install an operating system on the company test server for several days. The technician has experienced error messages at several points of theinstallation and the system has frozen during various parts of the boot process. The technician has replaced the power supply, graphics card and installation disk with known good components.Which of the following could be causing these issues?()AStorage driver not loadedBFragmented hard driveCDamaged or faulty NIC chipsetDDamaged or faulty system boardEMemory incompatible with the processorFMissing voltage regulator
单选题The technician has suspicions that a browser has been hijacked. Which of the following should the technician look for in this situation?()AA new default gateway has been setup.BA new Internet shortcut has been added.CA new web browser has been installed and is now the default.DA proxy server has been enabled.