单选题You recently created a database and configured the SPFILE with the following parameter settings to ensure that Oracle automatically adjusts the memory for the Program Global Area (PGA): SORT_AREA_SIZE = 150M HASH_AREA_SIZE = 150M BITMAP_MERGE_AREA_SIZE = 150M CREATE_BITMAP_AREA_SIZE = 150M WORKAREA_SIZE_POLICY = AUTO You have not included the PGA_AGGREGATE_TARGET initialization parameter in the SPFILE and the System Global Area (SGA) is currently sized at 4G. What is the total PGA memory allocated across all database server processes?()A 10MB 400MC 600MD 800M
单选题
You recently created a database and configured the SPFILE with the following parameter settings to ensure that Oracle automatically adjusts the memory for the Program Global Area (PGA): SORT_AREA_SIZE = 150M HASH_AREA_SIZE = 150M BITMAP_MERGE_AREA_SIZE = 150M CREATE_BITMAP_AREA_SIZE = 150M WORKAREA_SIZE_POLICY = AUTO You have not included the PGA_AGGREGATE_TARGET initialization parameter in the SPFILE and the System Global Area (SGA) is currently sized at 4G. What is the total PGA memory allocated across all database server processes?()
A
10M
B
400M
C
600M
D
800M
参考解析
解析:
暂无解析
相关考题:
Examine the parameter setting in your database:Which statement is correct about the database?() A. Automatic memory management is disabled because PGA_AGGREGATE_TARGET and SGA_TARGET are not setB. The instance is started but the database will not be opened until PGA_AGGREGATE_TARGET and SGA_TARGET are setC. The database is opened but users cannot perform transactions until PGA_AGGREGATE_TARGET and SGA_TARGET are setD. Automatic memory management is enabled and, as per policy, 60% of the memory for System Global Area (SGA) and 40% of the memory for Program Global Area (PGA) will be distributed at startup
You set the following parameters in the parameter file and restarted the database:Which two statements are true regarding these parameters after the database instance is restarted?() A. The MEMORY_MAX_TARGET parameter is automatically set to 500 MBB. The value of the MEMORY_MAX_TARGET parameter remains zero till it is changed manuallyC. The PGA_AGGREGATE_TARGET and SGA_TARGET parameters are automatically set to zeroD. The lower bounds of PGA_AGGREGATE_TARGET and SGA_TARGET parameters are set to 90 MB and 270 MB, respectively
You specify a nonzero value for the MEMORY_TARGET initialization parameter, but do not set the PGA_AGGREGATE_TARGET or the SGA_TARGET parameters. You restart your database instance.Which statement about the result is true?()A. The database instance starts, and Oracle sets the default value of SGA_TARGET to the same value as SGA_MAX_SIZEB. The database instance starts, and Oracle automatically tunes memory and allocates 60 percent to the SGA and 40 percent to the PGAC. The database instance starts, but Automatic Memory Management is disabledD. The database instance will not start because you did not specify the PGA_AGGREGATE_TARGET or SGA_TARGET parameter
You are maintaining an OLTP database in Oracle10g. You have configured the Flash Recovery Area in your database. The Flash Recovery Area is full because you have set the retention policy to NONE. What will you do to resolve the problem?()A、 Increase the value of the FAST_START_MTTR_TARGET initialization parameter.B、 Increase the value of the DB_RECOVERY_FILE_DEST_SIZE parameter.C、 Increase the value of the PGA_AGGREGATE_TARGET initialization parameter.D、 Increase the value of the SGA_TARGET initialization parameter.
The BACKUP_TAPE_IO_SLAVES parameter is set to FALSE for the database instance. Which statement is true while performing a tape backup in an RMAN session?() A、 The tape I/O performed is asynchronousB、 The tape buffer is allocated from the System Global Area (SGA)C、 The tape buffer is allocated from the Program Global Area (PGA)D、 Oracle I/O uses an interrupt mechanism to determine when each I/O completes
You specify a nonzero value for the MEMORY_TARGET initialization parameter,but do not set the PGA_AGGREGATE_TARGET or the SGA_TARGET parameters. You restart your database instance. Which statement about the result is true?()A、 The database instance starts,and Oracle sets the default value of SGA_TARGET to the same value as SGA_MAX_SIZEB、 The database instance starts,and Oracle automatically tunes memory and allocates 60 percent to the SGA and 40 percent to the PGAC、 The database instance starts,but Automatic Memory Management is disabledD、 The database instance will not start because you did not specify the PGA_AGGREGATE_TARGET or SGA_TARGET parameter
Your database is running in the automatic Program Global Area (PGA) memory management and Shared Memory Management mode. You want to increase the memory available for the SQL work areas. What would you do?()A、modify the HASH_AREA_SIZE initialization parameterB、modify the PGA_AGGREGATE_TARGET initialization parameterC、modify the WORK_AREASIZE_POLICY initialization parameterD、increase the value of the SGA_TARGET initialization parameterE、increase the value of the SGA_MAX_SIZE initialization parameterF、increase the value of the SORT_AREA_SIZE initialization parameter
You specify a nonzero value for the MEMORY_TARGET initialization parameter, but do not set thePGA_AGGREGATE_TARGET or the SGA_TARGET parameters. You restart your database instance.Which statement about the result is true?()A、The database instance starts, and Oracle sets the default value of SGA_TARGET to the same value as SGA_MAX_SIZEB、The database instance starts, and Oracle automatically tunes memory and allocates 60 percent to the SGA and 40 percent to the PGAC、The database instance starts, but Automatic Memory Management is disabledD、The database instance will not start because you did not specify the PGA_AGGREGATE_TARGET or SGA_TARGET parameter
Which statement about Automatic Memory Management with Oracle 11g is true?() A、 You cannot specify MEMORY_TARGET if you explicitly specify SGA_TARGET or PGA_AGGREGATE_ TARGET values that are greater than zero in your parameter file.B、 Oracle can reallocate memory between the SGA and PGA automatically as needed.C、 To use Automatic Memory Management, you must explicitly set both the MEMORY_TARGET and MEMORY_MAX_TARGET parameters in your parameter file.D、 You can set the MEMORY_TARGET parameter to a maximum value of the current SGA size plus the current PGA size.
Identify the memory component from which memory may be allocated for: () 1: Session memory for the shared server 2: Buffers for I/O slaves 3: Oracle Database Recovery Manager (RMAN) backup and restore operations A、Large PoolB、Redo Log BufferC、Database Buffer CacheD、Program Global Area (PGA)
SORT_AREA SIZE and HASH_AREA_SIZE parameters are ignored in some of the user sessions. What could be the reason?()A、The User Global Area (UGA) is not configured.B、The sessions were started using the login name SYS.C、The sessions are running in the Automatic Shared Memory Management mode.D、The sessions are running in the automatic Program Global Area (PGA) memory management mode.
You are enabling the Automatic Shared Memory Management feature in the Oracle Database 10g to ensure that the important memory structures of the System Global Area (SGA) are automatically adjusted depending on the database workload. You are using Enterprise Manager 10g to enable this feature. You are currently on the Administration tab page. Which two links should you click to go to the Memory Advisor page?() A、 Advisor CentralB、 Global AttributesC、 Resource MonitorsD、 Memory ParametersE、 Database Usage StatisticsF、 All Initialization ParametersG、 Automatic Workload Repository
You recently created a database and configured the SPFILE with the following parameter settings to ensure that Oracle automatically adjusts the memory for the Program Global Area (PGA): SORT_AREA_SIZE = 150M HASH_AREA_SIZE = 150M BITMAP_MERGE_AREA_SIZE = 150M CREATE_BITMAP_AREA_SIZE = 150M WORKAREA_SIZE_POLICY = AUTO You have not included the PGA_AGGREGATE_TARGET initialization parameter in the SPFILE and the System Global Area (SGA) is currently sized at 4G. What is the total PGA memory allocated across all database server processes?() A、 10MB、 400MC、 600MD、 800M
You are working in a dedicated server environment. Your database is running in the automatic Program Global Area (PGA) memory management mode. Which two statements are correct in this scenario?()A、The WORK_AREASIZE_POLICY initialization parameter cannot be set to AUTO.B、The Oracle database automatically controls the amount of PGA memory allotted to SQL work areas.C、Setting the value of the SGA_TARGET initialization parameter to 0 will disable the automatic PGA memory management.D、The SORT_AREA_SIZE parameter is ignored by all the sessions running in the automatic PGA memory management mode.
You have included the following parameter setting in your server parameter file: PGA_AGGREGATE_TARGET = 800M SORT_AREA_SIZE = 100M HASH_AREA_SIZE = 100M BITMAP_MERGE_AREA_SIZE = 100M CREATE_BITMAP_AREA_SIZE = 100M Which statement is true?() A、 All the *_AREA_SIZE parameters are ignored.B、 The Automatic PGA Memory Management feature cannot be disabled.C、 The total Program Global Area (PGA) memory cannot be manually increased above 800M.D、 The total memory for the PGA can automatically exceed 800M using the Automatic PGA Memory Management feature.
Identify the memory component from which memory may be allocated for:() 1. Session memory for the shared server 2. Buffers for I/O slaves 3. Oracle Database Recovery Manager (RMAN) backup and restore operationsA、Large PoolB、Redo Log BufferC、Database Buffer CacheD、Program Global Area (PGA)
单选题You specify a nonzero value for the MEMORY_TARGET initialization parameter, but do not set thePGA_AGGREGATE_TARGET or the SGA_TARGET parameters. You restart your database instance.Which statement about the result is true?()AThe database instance starts, and Oracle sets the default value of SGA_TARGET to the same value as SGA_MAX_SIZEBThe database instance starts, and Oracle automatically tunes memory and allocates 60 percent to the SGA and 40 percent to the PGACThe database instance starts, but Automatic Memory Management is disabledDThe database instance will not start because you did not specify the PGA_AGGREGATE_TARGET or SGA_TARGET parameter
单选题Examine the parameter setting in your database: Which statement is correct about the database?()A Automatic memory management is disabled because PGA_AGGREGATE_TARGET and SGA_TARGET are not setB The instance is started but the database will not be opened until PGA_AGGREGATE_TARGET and SGA_TARGET are setC The database is opened but users cannot perform transactions until PGA_AGGREGATE_TARGET and SGA_TARGET are setD Automatic memory management is enabled and, as per policy, 60% of the memory for System Global Area (SGA) and 40% of the memory for Program Global Area (PGA) will be distributed at startup
单选题SORT_AREA SIZE and HASH_AREA_SIZE parameters are ignored in some of the user sessions. What could be the reason?()AThe User Global Area (UGA) is not configured.BThe sessions were started using the login name SYS.CThe sessions are running in the Automatic Shared Memory Management mode.DThe sessions are running in the automatic Program Global Area (PGA) memory management mode.
多选题You are working in a dedicated server environment. Your database is running in the automatic Program Global Area (PGA) memory management mode. Which two statements are correct in this scenario? ()AThe WORK_AREASIZE_POLICY initialization parameter cannot be set to AUTO.BThe Oracle database automatically controls the amount of PGA memory allotted to SQL work areas.CSetting the value of the SGA_TARGET initialization parameter to 0 will disable the automatic PGA memory management.DThe SORT_AREA_SIZE parameter is ignored by all the sessions running in the automatic PGA memory management mode.
多选题You are enabling the Automatic Shared Memory Management feature in the Oracle Database 10g to ensure that the important memory structures of the System Global Area (SGA) are automatically adjusted depending on the database workload. You are using Enterprise Manager 10g to enable this feature. You are currently on the Administration tab page. Which two links should you click to go to the Memory Advisor page?()AAdvisor CentralBGlobal AttributesCResource MonitorsDMemory ParametersEDatabase Usage StatisticsFAll Initialization ParametersGAutomatic Workload Repository
单选题You have included the following parameter setting in your server parameter file: PGA_AGGREGATE_TARGET = 800M SORT_AREA_SIZE = 100M HASH_AREA_SIZE = 100M BITMAP_MERGE_AREA_SIZE = 100M CREATE_BITMAP_AREA_SIZE = 100M Which statement is true?()A All the *_AREA_SIZE parameters are ignored.B The Automatic PGA Memory Management feature cannot be disabled.C The total Program Global Area (PGA) memory cannot be manually increased above 800M.D The total memory for the PGA can automatically exceed 800M using the Automatic PGA Memory Management feature.
单选题Your database is running in the automatic Program Global Area (PGA) memory management and Shared Memory Management mode. You want to increase the memory available for the SQL work areas. What would you do?()Amodify the HASH_AREA_SIZE initialization parameterBmodify the PGA_AGGREGATE_TARGET initialization parameterCmodify the WORK_AREASIZE_POLICY initialization parameterDincrease the value of the SGA_TARGET initialization parameterEincrease the value of the SGA_MAX_SIZE initialization parameterFincrease the value of the SORT_AREA_SIZE initialization parameter
单选题The BACKUP_TAPE_IO_SLAVES parameter is set to FALSE for the database instance. Which statement is true while performing a tape backup in an RMAN session?()A The tape I/O performed is asynchronousB The tape buffer is allocated from the System Global Area (SGA)C The tape buffer is allocated from the Program Global Area (PGA)D Oracle I/O uses an interrupt mechanism to determine when each I/O completes
单选题Which statement about Automatic Memory Management with Oracle 11g is true?()A You cannot specify MEMORY_TARGET if you explicitly specify SGA_TARGET or PGA_AGGREGATE_ TARGET values that are greater than zero in your parameter file.B Oracle can reallocate memory between the SGA and PGA automatically as needed.C To use Automatic Memory Management, you must explicitly set both the MEMORY_TARGET and MEMORY_MAX_TARGET parameters in your parameter file.D You can set the MEMORY_TARGET parameter to a maximum value of the current SGA size plus the current PGA size.
单选题You specify a nonzero value for the MEMORY_TARGET initialization parameter, but do not set the PGA_AGGREGATE_TARGET or the SGA_TARGET parameters. You restart your database instance. Which statement about the result is true?()AThe database instance starts, and Oracle sets the default value of SGA_TARGET to the same value as SGA_MAX_SIZEBThe database instance starts, and Oracle automatically tunes memory and allocates 60 percent to the SGA and 40 percent to the PGACThe database instance starts, but Automatic Memory Management is disabledDThe database instance will not start because you did not specify the PGA_AGGREGATE_TARGET or SGA_TARGET parameter
单选题Your database is running on the automatic Program Global Area (PGA) memory management and Shared Memory Management mode. You want to increase the memory available for the SQL work areas. What would you do?()A modify the HASH_AREA_SIZE initialization parameterB modify the PGA_AGGREGATE_TARGET initialization parameterC modify the WORK_AREASIZE_POLICY initialization parameterD increase the value of the SGA_TARGET initialization parameterE increase the value of the SGA_MAX_SIZE initialization parameterF increase the value of the SORT_AREA_SIZE initialization parameter
单选题You recently created a database and configured the SPFILE with the following parameter settings to ensure that Oracle automatically adjusts the memory for the Program Global Area (PGA): SORT_AREA_SIZE = 150M HASH_AREA_SIZE = 150M BITMAP_MERGE_AREA_SIZE = 150M CREATE_BITMAP_AREA_SIZE = 150M WORKAREA_SIZE_POLICY = AUTO You have not included the PGA_AGGREGATE_TARGET initialization parameter in the SPFILE and the System Global Area (SGA) is currently sized at 4G. What is the total PGA memory allocated across all database server processes?()A 10MB 400MC 600MD 800M