单选题Using Oracle Scheduler you have scheduled two jobs, JOB_Aand JOB_B, to run at 9:00 p.m. every Friday. You want both the jobs to use a single resource plan, WEEKEND_PLAN. Which task must have already been performed to enable you to achieve this objective?()A A window must have been created with the WEEKEND_PLAN resource plan.B A program must have been created with the WEEKEND_PLAN resource plan.C A job class must have been created with the WEEKEND_PLAN resource plan.D A window group must have been created with the WEEKEND_PLAN resource plan.

单选题
Using Oracle Scheduler you have scheduled two jobs, JOB_Aand JOB_B, to run at 9:00 p.m. every Friday. You want both the jobs to use a single resource plan, WEEKEND_PLAN. Which task must have already been performed to enable you to achieve this objective?()
A

 A window must have been created with the WEEKEND_PLAN resource plan.

B

 A program must have been created with the WEEKEND_PLAN resource plan.

C

 A job class must have been created with the WEEKEND_PLAN resource plan.

D

 A window group must have been created with the WEEKEND_PLAN resource plan.


参考解析

解析: 暂无解析

相关考题:

Which two statements are true about a job chain?() A. A job chain can contain a nested chain of jobs.B. The jobs in a job chain cannot have more than one dependency.C. A job of the CHAIN type can be run using event-based or time-based schedules.D. The jobs in a job chain can be executed only by using the events generated by the Scheduler

For which two situations would you use functionality provided by the Resource Manager?() A. setting idle timeout limits on resource plansB. saving storage space by using compressed backup setsC. creating jobs that will run automatically at a scheduled timeD. assigning priorities to jobs to manage access to system resourcesE. creating alerts to perform notification when tablespaces are low on available space resources

You want to schedule a job to rebuild all indexes on the SALES table after the completion of a bulk load operation. The bulk load operation must also be a scheduled job that executes as soon as the first file that contains data arrives on the system.How would you create these jobs?()A. Create both jobs by using events raised by the schedulerB. Create both jobs by using events raised by the applicationC. Create a job to rebuild indexes by using events arised by the application and then create another job to perform bulk load by using events raised by the schedulerD. Create a job to rebuild indexes by using events arised by the Scheduler and then create another job to perform bulk load by using events raised by the application

For which two situations would you use functionality provided by the Resource Manager? ()(Choose two.) A. setting idle timeout limits on resource plansB. saving storage space by using compressed backup setsC. creating jobs that will run automatically at a scheduled timeD. assigning priorities to jobs to manage access to system resourcesE. creating alerts to perform notification when tablespaces are low on available space resources

Which two statements apply to policy scheduling?() (Choose two.) A. An individual policy can have only one scheduler applied.B. You must manually configure system-time updates.C. Multiple policies can use the same scheduler.D. Policies that do not have schedulers are not active.

Which two statements apply to policy scheduling?() (Choose two.)A、An individual policy can have only one scheduler applied.B、You must manually configure system-time updates.C、Multiple policies can use the same scheduler.D、Policies that do not have schedulers are not active.

While creating a job class using the DBMS_SCHEDULER package, you set the logging level to LOGGING_RUNS. What would be the impact of this setting?()A、 Oracle Scheduler would write detailed information to the job log for each run of each job in the job class.B、 Oracle Scheduler would write detailed information to the job log for the first run of each job in the job class.C、 Oracle Scheduler would write detailed information to the job log for each run of only the first job in the job class.D、 Oracle Scheduler would write detailed information for all operations performed on all jobs in the job class.

You work as a database administrator for Certkiller .com. You want to administer your database servers,which are running on different host machines,using the Web-enabled grid control interface. You have configured the agent on the host machines. You have started the Oracle Database 10g Grid Control utility on your machine. Which two additional components would you configure to achieve this objective?()A、Application Server ControlB、Oracle Management ServiceC、Oracle Enterprise Manager RepositoryD、Oracle Enterprise Manager Database Control

Using Oracle Scheduler you have scheduled two jobs, JOB_Aand JOB_B, to run at 9:00 p.m. every Friday. You want both the jobs to use a single resource plan, WEEKEND_PLAN. Which task must have already been performed to enable you to achieve this objective?()A、 A window must have been created with the WEEKEND_PLAN resource plan.B、 A program must have been created with the WEEKEND_PLAN resource plan.C、 A job class must have been created with the WEEKEND_PLAN resource plan.D、 A window group must have been created with the WEEKEND_PLAN resource plan.

Which two statements are true about a job chain? ()(Choose two.)A、A job chain can contain a nested chain of jobs.B、The jobs in a job chain cannot have more than one dependency.C、A job of the CHAIN type can be run using event-based or time-based schedules.D、The jobs in a job chain can be executed only by using the events generated by the Scheduler

Identify four uses of the Oracle Scheduler.()A、 enables Oracle database to schedule which processes execute on which processors in a multiple CPU environmentB、 enables Oracle database to do patches according to a DBA-defined scheduleC、 enables you to schedule the execution of jobs based on timeD、 enables you to execute jobs in a clustered environmentE、 enables you to periodically execute operating systemscript files located on the same server as the databaseF、 enables you to create a job that makes use of saved programs and schedulesG、 enables you to automate the management of the jobs that are created using the DBMS_JOB package

Which two statements are true about a job chain?()A、 A job chain can contain a nested chain of jobsB、 The jobs in a job chain cannot have more than one dependencyC、 A job of the CHAIN type can be run using event-based or time-based schedulesD、 The jobs in a job chain can be executed only by using the events generated by the Scheduler

Using Oracle Scheduler you have scheduled two jobs, JOB_A and JOB_B, to run at 9:00 p.m. every Friday. You want both the jobs to use a single resource plan, WEEKEND_PLAN. Which task must have already been performed to enable you to achieve this objective?()A、 A window must have been created with the WEEKEND_PLAN resource plan.B、 A program must have been created with the WEEKEND_PLAN resource plan.C、 A job class must have been created with the WEEKEND_PLAN resource plan.D、 A windows group must have been created with the WEEKEND_PLAN resource plan.

Which three components does the Scheduler use for managing tasks within the Oracle environment?()A、a jobB、a programC、a scheduleD、a PL/SQL procedure

For which two situations would you use functionality provided by the Resource Manager?()A、 setting idle timeout limits on resource plansB、 saving storage space by using compressed backup setsC、 creating jobs that will run automatically at a scheduled timeD、 assigning priorities to jobs to manage access to system resourcesE、 creating alerts to perform notification when tablespaces are low on available space resources

You have a file server named Server1 that runs Windows Server 2003 Service Pack 2 (SP2). You need to use Windows Backup to meet the following requirements: ·Minimize the number of scheduled backup jobs. ·Perform a scheduled normal backup to disk every Friday. ·Perform a scheduled normal backup to tape every Friday. ·Perform scheduled differential backups to tape every Monday, Tuesday, Wednesday, and Thursday. How many scheduled jobs should you create from Windows Backup? ()A、oneB、twoC、threeD、six

You are a network administrator for ExamSheet.net's Windows 2000 network.  You use a user account named User1 to log on tot a Windows 2000 Professional computer. The computer is used by different students in a classroom. User1 does not have administrative rights. However, you prefer to use this account for your daily activities. Using the Task Scheduler you schedule a task to run a command file named AddUsers.cmd that automatically adds six more student user accounts. You configure the task to run as the administrator account.  After the task was scheduled to have run you open the Task Scheduler and discover a status of "Could not start" for the task. You also discover account logon failure audit events in the computer's Security log.You want the scheduled task to successfully run AddUsers.cmd. You want to accomplish this with the least amount of administrative effort.  What should you do?()A、Schedule the task using theATcommand.B、Reenter the password for the administrator account using the Task Scheduler.C、Log on with an administrative account and reschedule the task.D、Log on by using the local Administrator account. Then schedule the task to run under User1.

多选题For which two situations would you use functionality provided by the Resource Manager? ()(Choose two.)Asetting idle timeout limits on resource plansBsaving storage space by using compressed backup setsCcreating jobs that will run automatically at a scheduled timeDassigning priorities to jobs to manage access to system resourcesEcreating alerts to perform notification when tablespaces are low on available space resources

单选题You schedule a task to run after 15 minutes. After an hour, you check the Event Viewer system log. It contains the error message: "The Task Scheduler service failed to start". You want to run the scheduled task again. What should you do before restarting the Task Scheduler? ()ASet the Task Scheduler service to log on as a Local System account.BSet the task scheduler service to interact with the desktop.CRestart the remote procedure service called RPC service.DLog off then on using an account in the power users group.

单选题Using Oracle Scheduler you have scheduled two jobs, JOB_Aand JOB_B, to run at 9:00 p.m. every Friday. You want both the jobs to use a single resource plan, WEEKEND_PLAN. Which task must have already been performed to enable you to achieve this objective?()A A window must have been created with the WEEKEND_PLAN resource plan.B A program must have been created with the WEEKEND_PLAN resource plan.C A job class must have been created with the WEEKEND_PLAN resource plan.D A window group must have been created with the WEEKEND_PLAN resource plan.

单选题While creating a job class using the DBMS_SCHEDULER package, you set the logging level to LOGGING_RUNS. What would be the impact of this setting?()A Oracle Scheduler would write detailed information to the job log for each run of each job in the job class.B Oracle Scheduler would write detailed information to the job log for the first run of each job in the job class.C Oracle Scheduler would write detailed information to the job log for each run of only the first job in the job class.D Oracle Scheduler would write detailed information for all operations performed on all jobs in the job class.

单选题You want to schedule a job to rebuild all indexes on the SALES table after the completion of a bulk load operation. The bulk load operation must also be a scheduled job that executes as soon as the first file that contains data arrives on the system. How would you create these jobs?()ACreate both jobs by using events raised by the schedulerBCreate both jobs by using events raised by the applicationCCreate a job to rebuild indexes by using events arised by the application and then create another job to perform bulk load by using events raised by the schedulerDCreate a job to rebuild indexes by using events arised by the Scheduler and then create another job to perform bulk load by using events raised by the application

多选题For which two situations would you use functionality provided by the Resource Manager?()Asetting idle timeout limits on resource plansBsaving storage space by using compressed backup setsCcreating jobs that will run automatically at a scheduled timeDassigning priorities to jobs to manage access to system resourcesEcreating alerts to perform notification when tablespaces are low on available space resources

多选题Which two statements are true about a job chain? ()(Choose two.)AA job chain can contain a nested chain of jobs.BThe jobs in a job chain cannot have more than one dependency.CA job of the CHAIN type can be run using event-based or time-based schedules.DThe jobs in a job chain can be executed only by using the events generated by the Scheduler

单选题Using Oracle Scheduler you have scheduled two jobs, JOB_A and JOB_B, to run at 9:00 p.m. every Friday. You want both the jobs to use a single resource plan, WEEKEND_PLAN. Which task must have already been performed to enable you to achieve this objective?()A A window must have been created with the WEEKEND_PLAN resource plan.B A program must have been created with the WEEKEND_PLAN resource plan.C A job class must have been created with the WEEKEND_PLAN resource plan.D A windows group must have been created with the WEEKEND_PLAN resource plan.

多选题Identify four uses of the Oracle Scheduler.()Aenables Oracle database to schedule which processes execute on which processors in a multiple CPU environmentBenables Oracle database to do patches according to a DBA-defined scheduleCenables you to schedule the execution of jobs based on timeDenables you to execute jobs in a clustered environmentEenables you to periodically execute operating systemscript files located on the same server as the databaseFenables you to create a job that makes use of saved programs and schedulesGenables you to automate the management of the jobs that are created using the DBMS_JOB package

多选题Which two statements are true about a job chain?()AA job chain can contain a nested chain of jobs.BThe jobs in a job chain cannot have more than one dependency.CA job of the CHAIN type can be run using event-based or time-based schedules.DThe jobs in a job chain can be executed only by using the events generated by the Scheduler

多选题Which two statements are true about a job chain?()AA job chain can contain a nested chain of jobsBThe jobs in a job chain cannot have more than one dependencyCA job of the CHAIN type can be run using event-based or time-based schedulesDThe jobs in a job chain can be executed only by using the events generated by the Scheduler