单选题A safety management system that satisfies the requirements of the ISM Code is a system of prevention designed to prevent pollution and improve safety. The safety management system shall include the following functional requirements, please find out the non applicable function().AA safety and environmental protection policy;BInstructions and procedures to ensure safety operation of ships and protection of the environment in compliance with relevant international and flag state legislationCProvide a guarantee that there will never be another accident or technical defectDDefined levels of authority and lines of communication between and amongst, shore and shipboard personnel

单选题
A safety management system that satisfies the requirements of the ISM Code is a system of prevention designed to prevent pollution and improve safety. The safety management system shall include the following functional requirements, please find out the non applicable function().
A

A safety and environmental protection policy;

B

Instructions and procedures to ensure safety operation of ships and protection of the environment in compliance with relevant international and flag state legislation

C

Provide a guarantee that there will never be another accident or technical defect

D

Defined levels of authority and lines of communication between and amongst, shore and shipboard personnel


参考解析

解析: 暂无解析

相关考题:

The purpose of the requirements definition phase is to produce a clear, complete, consistent, and testable(71 )of the technical requirements for the software product.During the requirements definition phase, the requirements definition team uses an iterative process to expand a broad statement of the system requirements into a complete and detailed specification of each function that the sofrware must perform. and each(72)that it must meet. The starting point is usually a set of high-level requirements from the(73)that describe the project or problem.In either case, the requirements definition team formulates an overall concept for the system and then defines(74)showing how the system will be operated, publishes the system and operations concept document, and conducts a system concept review(SCR).Following the SCR, the team derives(75)requirements for the system from the high level requirements and the system and operations concept. Using structured or object-oriented analysis, the team specifies the software functions and algorithms needed to satisfy each detailed requirement.A.functionB.definitionC.specificationD.statement

The purpose of systems analysis phase is to build a logical model of the new system. The first step is( ), where you investigate business processes and document what the new system must do to satisfy users. This step continues the investigation that began during the( ). You use the fact-finding results to build business models, data and process models, and object models. The deliverable for the systems analysis phase is the( ), which describes management and user requirements, costs and benefits, and outlines alternative development strategies. The purpose of the systems design phase is to create a physical model that will satisfy all documented requirements for the system. During the systems design phase, you need to determine the( ), which programmers will use to transform the logical design into program modules and code. The deliverable for this phase is the( ), which is presented to management and users for review and approval.A.System logical modelingB.use case modelingC.requirements modelingD.application modeling A.systems planning phaseB.systems modeling phaseC.systems analysis phaseD.systems design phase A.system charterB.system scope definitionC.system blueprintD.system requirement document A.application architectureB.system data modelC.system process modelD.implement environment A.system architecture descriptionB.system design specificationC.system technique architectureD.physical deployment architecture

A requirement is simply a statement of what the system must do or what characteristics it needs to have. Requirements written from the perspective of user and focus on user needs are called( ). Requirements written from the developers perspective and describe how the system will be implemented are called( ). Requirements evolve from detailed statemens of business capabilities that a system should have to detailed statements of the technical way in which the capabilities will be implemented in the new system. Requirements can be either functional or nofunctional in nature. For example, during the analysis phase of travel vehicles sales system, the system that must have the ability to search for available inventory is( ). The requirement that the system should be able to work on any Web browser belongs to( ). That customer personal information is protected in compliance with the Data Protection Act is a requirement of( ).A.operational requirements B.business requirements C.technical requirements D.system requirements A.operational requirements B.business requirements C.technical requirements D.system requirements A.a functional requirements B.a technical requirements C.an operational requirements D.a service requirements A.functional requirements B.technical requirements C.operational requirements D.information requirements A.system constraint B.system performance C.secrity and control D.cultural and political

______ is not among the Safety management objectives of the Company.A.to provide for safe practices in ship operation and a safe working environmentB.to establish safeguards against all identified risksC.to continuously improve safety management skills of personnel ashore and aboard ships,including preparing for emergencies related both to safety and environmental protectionD.to avoid damage to the environment,in particular,to the marine environment,and to property

The purpose of the requirements definition phase is to produce a clear,complete,consistent,and testable( )of the technical requirements for the software product.During the requirements definition phase,the requirements definition team uses an iterative process to expand a broad statement of the system requirements into a complete and detailed specification of each function that the software must perform and each(请作答此空)that it must meet.The starting point is usually a set of high level requirements from the( )that describe the project or problem.In either case,the requirements definition team formulates an overall concept for the system and then defines( )showing how the system will be operated publishes the system and operations concept document and conducts a system concept review(SCR).Following the SCR,the team derives( )requirements for the system from the high level requirements and the system and operations concept.using structured or object-oriented analysis.the team specifies the software functions and algorithms needed to satisfy each detailed requirement.A.criterionB.standardC.modelD.system

The purpose of the systems analysis phase is to build a logical model of the new system.The first step is(71),where you investigate business processes and document what the new system must do to satisfy users. This step continues the investigation that began during the(72). You use the fact-finding results to build business models,data and process models,and object models. The deliverable for the systems analysis phase is the(73),which describes management and user requirements,costs and benefits,and outlines alternative development strategies.The purpose of the systems design phase is to create a physical model that will satisfy all documented requirements for the system. During the systems design phase,you need to determine the(74),which programmers will use to transform the logical design into program modules and code. The deliverable for this phase is the(75),which is presented to management and users for review and approval.A.system charterB.system scope definitionC.system blueprintD.system requirements document

The purpose of the systems analysis phase is to build a logical model of the new system.The first step is(71),where you investigate business processes and document what the new system must do to satisfy users. This step continues the investigation that began during the(72). You use the fact-finding results to build business models,data and process models,and object models. The deliverable for the systems analysis phase is the(73),which describes management and user requirements,costs and benefits,and outlines alternative development strategies.The purpose of the systems design phase is to create a physical model that will satisfy all documented requirements for the system. During the systems design phase,you need to determine the(74),which programmers will use to transform the logical design into program modules and code. The deliverable for this phase is the(75),which is presented to management and users for review and approval.A.system architecture descriptionB.system design specificationC.system technique architectureD.physical deployment architecture

The purpose of the systems analysis phase is to build a logical model of the new system.The first step is(71),where you investigate business processes and document what the new system must do to satisfy users. This step continues the investigation that began during the(72). You use the fact-finding results to build business models,data and process models,and object models. The deliverable for the systems analysis phase is the(73),which describes management and user requirements,costs and benefits,and outlines alternative development strategies.The purpose of the systems design phase is to create a physical model that will satisfy all documented requirements for the system. During the systems design phase,you need to determine the(74),which programmers will use to transform the logical design into program modules and code. The deliverable for this phase is the(75),which is presented to management and users for review and approval.A.system logical modelingB.use case modelingC.requirements modelingD.application modeling

The purpose of the systems analysis phase is to build a logical model of the new system.The first step is(71),where you investigate business processes and document what the new system must do to satisfy users. This step continues the investigation that began during the(72). You use the fact-finding results to build business models,data and process models,and object models. The deliverable for the systems analysis phase is the(73),which describes management and user requirements,costs and benefits,and outlines alternative development strategies.The purpose of the systems design phase is to create a physical model that will satisfy all documented requirements for the system. During the systems design phase,you need to determine the(74),which programmers will use to transform the logical design into program modules and code. The deliverable for this phase is the(75),which is presented to management and users for review and approval.A.application architectureB.system datA.modelC.system process modelD.implement environment

( ) is the process of documenting. Analyzing,tracing,prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project. A.Integrated management B.Configuration management C.Scope management D.Requirements management

The architecture design specifies the overall architecture and the placement of software and hardware that will be used. Architecture design is a very complex process that is often left to experienced architecture designers and consultants. The first step is to refine the () into more detailed requirements that are then employed to help select the architecture to be used and the software components to be placed on each device. In a (), one also has to decide whether to use a two-tier, three-tier, or n-tier architecture. Then the requirements and the architecturedesign are used to develop the hardware and software specification. There are four primary types of nonfunctional requirements that can be important in designing the architecture. () specify the operating environment(s) in which the system must perform and how those may change over time. () focus on the nonfunctional requirements issues such as response time, capacity, and reliability. (请作答此空 ) are the abilities to protect the information system from disruption and data loss, whether caused by an intentional act. Cultural and political requirements are specific to the countries in which the system will be used. A. Safety requirements安全要求B. Security requirements安全要求C. Data management requirements数据管理要求D. System requirements 系统要求

Accelerated analysis approaches emphasize the construction of( )to more rapidly identify business and user requirements for a new system. As an accelerated analysis technology,( )reads the program code and automatically generates the equivalent system model, and the code can be obtained from ( ). All system analysis approaches require some form of(请作答此空)which includes those techniques to be used to identify or extract system problems and solution requirements from user community. ( )is a classical set of techniques used to collect information about system problems, opportunities, solution requirements, and priorities. A. requirement discoveryB. business process redesignC. cause-and-effect analysisD. total quality management

A customer wants to install a pSeries system into an OEM rack.  What critical information is provided in the Site and Hardware Planning Information manual?()A、System dimensions and weight, system power and cooling requirements, and list of supported OEM racksB、System dimensions and weight, list of supported OEM racks, and requirements for installing IBM systems into OEM racksC、System performance specs, system power and cooling requirements, and requirements for installing IBM systems into OEM racksD、System dimensions and weight, system power and cooling requirements, and requirements for installingIBM systems into OEM racks

安全系统 safety system

()is the management system to control the material consumed, reduce inventory in the manufacture company.A、DRP (Distribution Resource Planning)B、LRP (Logistics Resource Planning)C、MRP (Material Requirements Planning)D、ERP (Enterprise Resource Planning)

A company is looking to improve upon their current remote management capabilities.  Thecompany must ensure that access is removed from all systems when a user is terminated and that administrators can remotely manage a system’s BIOS.  Which of the following remote management systems would support both these requirements?()A、Remote management cardB、Terminal servicesC、Remote desktopD、LDAP enabled IP KVM

单选题General radio communications in the global system are those between()concerning the management and operation of the ships and may have impact on their safety.ASAR party and the ship in distressBSAR authorities and the ship in distress and survival craftCA ship station and any coast stationDShip stations and shore-based communication network

单选题A customer wants to install a pSeries system into an OEM rack.  What critical information is provided in the Site and Hardware Planning Information manual?()ASystem dimensions and weight, system power and cooling requirements, and list of supported OEM racksBSystem dimensions and weight, list of supported OEM racks, and requirements for installing IBM systems into OEM racksCSystem performance specs, system power and cooling requirements, and requirements for installing IBM systems into OEM racksDSystem dimensions and weight, system power and cooling requirements, and requirements for installingIBM systems into OEM racks

单选题The Company should clearly define and document the master’s responsibility with regard to all the following items except().Aimplementing the safety and environmental protection policy of the CompanyBpreparing procedures to respond to emergency situationsCverifying that specified requirements are observedDreviewing the SMS and reporting its deficiencies to the shore based management

单选题International Management Code for the safety operation of ships and for pollution prevention is simplified as ()AISM CodeBSOLAS 74 ConventionCSafety Management SystemDMARPOL Convention

单选题What is the primary objective of the plan phase()AAssess the existing environments to determine if it can support the proposed system.BIdentify the activities for installing and configuring the equipment at the customer sites.CGather high-level solution requirements, and understand the customer business needs an the opportunity.DPrepare the activities for day-to-day support, management, and monitoring of the newly implemented system.

单选题Ships do not permitted to the TBT paint after 2008,It is required by()Athe International Convention for the Safety of the Life at SeaBthe International Convention for the Prevention from shipsCthe International Convention on control of harmful anti-fouling system on shipsDthe International Convention for the Control and Management of Ship’s Ballast Water and Sediments

单选题During PSC inspection related to the ISM Code, of the Safety Management System (SMS) should be carried out if clear grounds are established()Aa less favorable inspectionBa more favorable inspectionCa less detailed inspectionDa more detailed inspection

单选题()is not among the Safety management objectives of the Company.Ato provide for safe practices in ship operation and a safe working environmentBto establish safeguards against all identified risksCto continuously improve safety management skills of personnel ashore and aboard ships,including preparing for emergencies related both to safety and environmental protectionDto avoid damage to the environment,in particular,to the marine environment,and to property

单选题The safety management objectives of the ISM Code are ().Ato provide for safe practices in ship operation and a safe working environmentBto establish safeguards against all identified risksCto continuously improve safety management skills of personnel, including preparing for emergenciesDall the above

单选题According to the functional requirements for a Safety Management System, every company should develop, () and () a SMS.Aimplement;verifyBmaintain;improveCimplement;maintainDreview;access

单选题The company should establish procedures by which()receive relevant information on the safety management system in working language or language understood by them.ANew personnelBThe ship's personnelCPersonnel transferred to new assignmentsDVisitor