149 As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:A. Insignificant.B. Reduced.C. Unchanged.D. Increased.E. Doubled
149 As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:
A. Insignificant.
B. Reduced.
C. Unchanged.
D. Increased.
E. Doubled
相关考题:
The basic terminology for networks includes:A.Activities, events, manpower, skill levels and slack.B.Activities, documentation, events, manpower and skill levels.C.Slack, activities, events, and time estimates.D.Time estimates, slack, sponsorship involvement, and activities.E.Time estimates, slack time, report writing, life cycle phases, and crashing times.
113 The basic terminology for networks includes:A. Activities, events, manpower, skill levels and slack.B. Activities, documentation, events, manpower and skill levels.C. Slack, activities, events, and time estimates.D. Time estimates, slack, sponsorship involvement, and activities.E. Time estimates, slack time, report writing, life cycle phases, and crashing times
195 The basic terminology for networks includes:A. Activities, events, manpower, skill levels and slack.B. Activities, documentation, events, manpower and skill levels.C. Slack, activities, events, and time estimates.D. Time estimates, slack, sponsorship involvement, and activities.E. Time estimates, slack time, report writing, life cycle phases, and crashing times
为了核查电路是否满足规定的时钟频率需求,则需要在逻辑综合后生成时序 报告(report)进行检查;同时重点关注该报告的slack,若slack 0,则该电路工作频率不满足需求(说明:请填入大于或者小于)。
建立时间的时序报告中slack大于等于0,则该电路工作频率不满足规定的时钟频率需求。