单选题Company.com is adding a new I/O drawer to an existing p5-570 with four LPARs and wants to re-balance the network cards in the I/O drawers. What is the best way to accomplish this?()AAdd the devices as virtual adapters to a VIO server first,then add the I/O drawer and create the shared ethernet adaptersBPower down the partitions,run the diag a command when the system is brought back up and reconfigure the network cardsCUse the rmdev command to remove the devices,shut down the partitions and move the cads,then run the cfgmgr command after rebootDDetach the network cards,run rmdev on the devices and then dynamically reassign theadapters to the partitions and reconfigure

单选题
Company.com is adding a new I/O drawer to an existing p5-570 with four LPARs and wants to re-balance the network cards in the I/O drawers. What is the best way to accomplish this?()
A

Add the devices as virtual adapters to a VIO server first,then add the I/O drawer and create the shared ethernet adapters

B

Power down the partitions,run the diag a command when the system is brought back up and reconfigure the network cards

C

Use the rmdev command to remove the devices,shut down the partitions and move the cads,then run the cfgmgr command after reboot

D

Detach the network cards,run rmdev on the devices and then dynamically reassign theadapters to the partitions and reconfigure


参考解析

解析: 暂无解析

相关考题:

Click the Exhibit button. Which three code fragments, added individually at line 29, produce the output 100?() A.n = 100;B.i.setX( 100 );C.o.getY().setX( 100 );D.i = new Inner(); i.setX( 100 );E.o.setY( i ); i = new Inner(); i.setX( 100 );F.i = new Inner(); i.setX( 100 ); o.setY( i );

public class Something {public static void main(String[] args) {Other o = new Other();new Something().addOne(o);}public void addOne(final Other o) {o.i++;}}class Other {public int i;}和上面的很相似,都是关于final 的问题,这有错吗?

A new router is added to an existing HSRP standby group. One of the existing routers is in anactive state, the other is in a standby state. Under what circumstance will the new router becomethe active router?()A、The new router will become active immediately because it’s the newest router introduced intothe groupB、The new router can become active only when the existing active router and the existing standbyrouter become unavailableC、The new router has a lower priority valueD、The new router will never become active unless the existing active router becomes unavailableE、The new router has preempt configured and a higher priorityF、The new router has a higher priority value

Company.com complains that an outage is required when adding a new filesystem to cluster. The  System management function of HACMP (C-SPOC) functions in which manner when adding filesystems to a cluster?()  A、 Adds to all nodes with the cluster running.B、 Adds to all nodes with the cluster stopped.C、 Adds with the cluster running,uses "Lazy Update" to perform the logical volume synchronization.D、 Adds to all nodes with the cluster running but requires the volume groups to be exported andimported after.

When booting the p5 590 server in full system partition mode, which location is preferred for the fastest boot?()A、A SAN deviceB、First I/O drawerC、Any I/O drawer within the main frameD、First I/O drawer within the expansion frame

A p5-570 8-way 32GB system has been proposed to a customer as a new test system with four LPARs.  The current applications are certified on AIX 5.2 but not yet on AIX 5.3.  The customer wants to understand the advantages and disadvantages of this solution versus a pair of 4-way p5-550s with 16GB each in testing their current applications. Which of the following points should the pSeries technical specialist highlight?()A、The p5-570 would save rack space over a pair of p5-550 servers.B、The p5-570 allows for more CPU and memory resources to be dynamically allocated to any LPAR for performance testing.C、The p5-570 can only be upgraded to 64GB of RAM without replacing memory.D、The p5-570 supports advanced features such as Micro-Partitioning and Virtual I/O allowing more LPARs of the customer’s applications with fewer processors and fewer I/O adapters.

The pSeries technical specialist is designing a two LPAR p5-570 with eight total processors.  The system is a test system to run AIX 5.2.  The customer has stated a preference for internal disks for the boot devices.  The customer has said they may later need to run three or four LPARs without increasing the number of processors. What should the pSeries technical specialist tell the customer about the ability of the p5-570 to meet their requirements?()A、It will require additional SCSI adapters and I/O drawers or external disks to support more than two LPARs.B、It has sufficient built-in SCSI controllers and disk enclosures to support four total LPARs by only adding the necessary additional disks.C、It is unable to use internal disks for LPARs and therefore additional adapters I/O drawers or external disks must be used to support all LPARs.D、It can support six LPARs with internal disks but will require special features, cables and an adapter to support the additional LPARs with internal disks.

What is a design consideration when using existing PCIe I/O drawers in a maximum bandwidth/throughput configuration on a new Power 750 system?()A、The new system requires 1 installed processor card for the GX++ bus adapterB、The new system requires a minimum of 2 installed processor cards for the GX++ bus adapterC、The new system requires a minimum of 3 installed processor cards and the HPC InfiniBand cluster adapterD、The new system requires 1 installed processor card for the GX++ bus adapter and the HPC InfiniBand cluster adapter

A customer has a Power 750 with the following: One processor card with 8 cores enabled, and 64GB RAM installed One GX+ adapter with one I/O drawer attached; One 4-port 1Gbps IVE adapterPowerVM Standard Edition; They need to add a GX++ adapter and cable it to an I/O drawer. Which of the following must also be ordered?()A、A second IVE adapterB、A second processor cardC、PowerVM Enterprise EditionD、An additional cable-management arm

A customer currently has five partitioned POWER4 systems and is adding new systems.  When the pSeries technical specialist introduces the first p5 system with CoD into this environment, how should the HMC be handled?()A、Order a new HMC to support the p5 system.B、Attach the new p5 system to the existing HMC.C、Upgrade the existing HMC to accommodate both the POWER4 and p5 systems.D、Do nothing.  This system does not require an HMC.

A Power 770 customer needs to add additional I/O adapters.  There is no room for the cards, so an I/O drawer must be added. What resource will help identify supported I/O drawers and the maximum number of drawers permitted per loop?()A、I/O Planning GuideB、Power Systems data sheetC、Power Systems Facts and FeaturesD、Run FLRT to recommend I/O features

Company.com is ordering a new p5-570 and planning for the option of using Capacity on  Demand to activate additional resources in the future. Which of the following is a prerequisite to support the addition of CPUs or memory without an outage?()A、Use Micro-PartitioningB、Configure a Virtual I/O ServerC、Configure dynamic logical partitionsD、Activate Advanced POWER Virtualization

A customer plans to consolidate two 8-core POWER6 systems with a total of 8 PCI-X adapters, 6 PCIe adapters, and a PCI-X I/O drawer into a 16-core Power 750. Which action allows the most efficient use of existing equipment?()A、Populate the Power 750 first then add a GX+ adapter to support PCI-X and PCIe I/O drawer loops.B、Populate the Power 750 first then add 2 GX+ adapters to support PCI-X and PCIe I/O drawer loops.C、Populate the Power 750 first then add a GX++ adapter to support PCI-X and PCIe I/O drawer loops.D、Populate the Power 750 first then add GX+ and GX++ adapters to support PCI-X and PCIe I/O drawer loops.

Company.com is adding a new I/O drawer to an existing p5-570 with four LPARs and wants to re-balance the network cards in the I/O drawers. What is the best way to accomplish this?()A、Add the devices as virtual adapters to a VIO server first,then add the I/O drawer and create the shared ethernet adaptersB、Power down the partitions,run the diag a command when the system is brought back up and reconfigure the network cardsC、Use the rmdev command to remove the devices,shut down the partitions and move the cads,then run the cfgmgr command after rebootD、Detach the network cards,run rmdev on the devices and then dynamically reassign theadapters to the partitions and reconfigure

10. class Inner {  11. private int x;  12. public void setX( int x) { this.x = x; }  13. public int getX() { return x; }  14. }  15.  16. class Outer {  17. private Inner y;  18. public void setY( Inner y) { this.y = y; }  19. public Inner getY() { return y; }  20. }  21.  22. public class Gamma {  23. public static void main( String[] args) { 24. Outer o = new Outer(); 25. Inner i = new Inner();  26.int n=10;  27. i.setX(n);  28. o.setY(i);  29. // insert code here  30. System.out.println( o.getY().getX());  31. }  32. }  Which three code fragments, added individually at line 29, produce the output 100?()A、 n = 100;B、 i.setX( 100);C、 o.getY().setX( 100);D、 i = new Inner(); i.setX( 100);E、 o.setY( i); i = new Inner(); i.setX( 100);F、 i = new Inner(); i.setX( 100); o.setY( i);

Using a policy with the policy-rematch flag enabled, what happens to the existing and new sessionswhen you change the policy action from permit to deny? ()A、The new sessions matching the policy are denied. The existing sessions are dropped.B、The new sessions matching the policy are denied. The existing sessions, not being allowed to carry any traffic, simply timeout.C、The new sessions matching the policy might be allowed through if they match another policy. The existing sessions are dropped.D、The new sessions matching the policy are denied. The existing sessions continue until they are completed or their timeout is reached.

How can an Oracle WebLogic cluster’s capacity be increased ?()A、 by adding server instances to the cluster on an existing machineB、 by adding machines to host server for more clustered instancesC、 by adding machines to the cluster to host the incremental server instancesD、 by adding node managers to an existing machine

You need to design a domain model that meets the company business and security requirements for controlling access to the new Web-based ordering application. What should you do?()A、Create a child OU within the existing domainB、Create a child domain of the existing domainC、Create a new domain in a new forest. Configure the new domain to trust the existing domainD、Create a new tree in the existing forest. Configure the new domain to trust the existing domain

单选题A Power 770 customer needs to add additional I/O adapters.  There is no room for the cards, so an I/O drawer must be added. What resource will help identify supported I/O drawers and the maximum number of drawers permitted per loop?()AI/O Planning GuideBPower Systems data sheetCPower Systems Facts and FeaturesDRun FLRT to recommend I/O features

单选题What is a design consideration when using existing PCIe I/O drawers in a maximum bandwidth/throughput configuration on a new Power 750 system?()AThe new system requires 1 installed processor card for the GX++ bus adapterBThe new system requires a minimum of 2 installed processor cards for the GX++ bus adapterCThe new system requires a minimum of 3 installed processor cards and the HPC InfiniBand cluster adapterDThe new system requires 1 installed processor card for the GX++ bus adapter and the HPC InfiniBand cluster adapter

单选题The pSeries technical specialist is designing a two LPAR p5-570 with eight total processors.  The system is a test system to run AIX 5.2.  The customer has stated a preference for internal disks for the boot devices.  The customer has said they may later need to run three or four LPARs without increasing the number of processors. What should the pSeries technical specialist tell the customer about the ability of the p5-570 to meet their requirements?()AIt will require additional SCSI adapters and I/O drawers or external disks to support more than two LPARs.BIt has sufficient built-in SCSI controllers and disk enclosures to support four total LPARs by only adding the necessary additional disks.CIt is unable to use internal disks for LPARs and therefore additional adapters I/O drawers or external disks must be used to support all LPARs.DIt can support six LPARs with internal disks but will require special features, cables and an adapter to support the additional LPARs with internal disks.

单选题A new router is added to an existing HSRP standby group. One of the existing routers is in anactive state, the other is in a standby state. Under what circumstance will the new router becomethe active router?()AThe new router will become active immediately because it’s the newest router introduced intothe groupBThe new router can become active only when the existing active router and the existing standbyrouter become unavailableCThe new router has a lower priority valueDThe new router will never become active unless the existing active router becomes unavailableEThe new router has preempt configured and a higher priorityFThe new router has a higher priority value

单选题A customer wants to migrate their existing cluster onto new POWER6 hardware, and in addition requires thecluster to be migrated from PowerHA version 5.3 to 5.5. Given that AIX 6.1 and PowerHA 5.5 filesets arealready installed in the new hardware, which of the following methods would allow the customer to maintaintheir current cluster configuration?()AAdd the new nodes to the existing cluster, and perform a rolling migration and remove the original nodesfrom the clusterBAdd the new nodes to the existing cluster, and perform a non-disruptive upgrade and remove the originalnodes from the cluster.CCreate a snapshot of the existing cluster and apply the snapshot to the new cluster. Start cluster serviceson the new cluster and stop the original clusterDCreate a snapshot of the existing cluster and apply the snapshot to the new cluster. Stop cluster serviceson the original cluster and start on the new cluster

单选题Company.com has recently received a new p5-570 in the data center and wants to Micro-Partition the server. The customer already has an existing HMC connected to a p690. Which of the following actions should the technical specialist take?()AOrder a POWER5 HMCBConnect to the existing HMCCInstall an 8-port asynchronous card in the managed server to connect to the existing HMCDInstall an additional network card to the existing HMC and connect to the POWER5 service processor

多选题How can an Oracle WebLogic cluster’s capacity be increased ?()Aby adding server instances to the cluster on an existing machineBby adding machines to host server for more clustered instancesCby adding machines to the cluster to host the incremental server instancesDby adding node managers to an existing machine

单选题Company.com has recently received a new p5-570 in the data center and intends to Micro-Partition the server. In which order should installation steps be taken?()AConnect to the network,power on the server,Micro-Partition the serverBConnect to the HMC,power on the server,Micro-Partition the server,connect to the networkCPower on server,connect to the network,Micro-Partition the server,connect to the HMCDPower on the server,connect to the HMC,Micro-Partition the server,connect to the network

单选题A customer has a Power 750 with the following: One processor card with 8 cores enabled, and 64GB RAM installed One GX+ adapter with one I/O drawer attached One 4-port 1Gbps IVE adapter PowerVM Standard Edition. They need to add a GX++ adapter and cable it to an I/O drawer. Which of the following must also be ordered?()AA second IVE adapterBA second processor cardCPowerVM Enterprise EditionDAn additional cable-management arm

单选题When booting the p5 590 server in full system partition mode, which location is preferred for the fastest boot?()AA SAN deviceBFirst I/O drawerCAny I/O drawer within the main frameDFirst I/O drawer within the expansion frame