单选题An administrator will be performing a PowerHA upgrade on a cluster from version 5.3 to version 5.5. Which ofthe following tasks will verify a successful migration?()AUse the clstat command and verify the cluster is in a stable stateBAfter each node is upgraded, run a verification and synchronizationCAfter all nodes are upgraded, run a verification and synchronizationDTake a snapshot of each node and verify the configuration is the same

单选题
An administrator will be performing a PowerHA upgrade on a cluster from version 5.3 to version 5.5. Which ofthe following tasks will verify a successful migration?()
A

Use the clstat command and verify the cluster is in a stable state

B

After each node is upgraded, run a verification and synchronization

C

After all nodes are upgraded, run a verification and synchronization

D

Take a snapshot of each node and verify the configuration is the same


参考解析

解析: 暂无解析

相关考题:

单选题A customer is planning a PowerHA cluster split across two sites. The sites are located 10km apart. There is aDS8000 storage array at each site with SAN connectivity between the two arrays. There are only enough IPinterfaces for one IP network in this cluster. How can they ensure that disk data is automatically mirrored and synchronized between sites?()APurchase PowerHA/XD licenseBPurchase PowerHA with GLVM licenseCImplement PowerHA with split-site LVMDImplement PowerHA with cross-site LVM

单选题An administrator has made several topology and resource group changes on one node in a running cluster.During verification and synchronization, using the "Emulate" option, many errors are reported. Theadministrator decided the best course of action was to roll back the changes. Prior to the changes beingmade, a cluster snapshot was taken. Which of the following actions will roll back the changes with the least disruption?()APerform a synchronization from a node without the changes.BApply the cluster snapshot on both nodes while the cluster is running.CRestore HACMP Configuration Database from Active Configuration on the node where the changes weremadeDStop the cluster using the option Unmanage Resource Groups and apply the cluster snapshot on thenode where the changes were made

单选题What is the fast path for the top level of C-SPOC within SMIT?()AcspocBcladminCcl_adminDcl_cspoc

单选题A customer synchronizes the cluster in a virtualized environment. During the process the following warning isdisplayed: "For nodes with a single Network Interface Card per logical network configured, it is recommended to includethe file ’/usr/es/sbin/cluster/netmon.cf’ with a pingable IP address as described in the PowerHA PlanningGuide". What should the customer do next?()AIgnore the warning as synchronization completed successfully.BPopulate the /usr/es/sbin/cluster/netmon.cf file with one or many IP addresses external to the cluster.CCreate another virtual adapter on each node and set-up PowerHA networking in a more traditional fashionDPopulate the /usr/es/sbin/cluster/netmon.cf file with any of the boot IP addresses on one of the othercluster nodes

单选题An administrator has a two-node PowerHA cluster in a mutual takeover configuration. He needs to updatefrom 5.5 service pack 1 to 5.5 service pack 2. Which of the following actions will perform the updates with norisk of disruption to applications running in the cluster?()AUnmanage resource groups on all nodes, update the cluster filesets, start cluster services on all nodes,ensure cluster services stabilizeBUpdate the cluster filesets on all nodes. Run ’refresh -s clstrmgrES’ on one node, wait for the cluster tostabilize, repeat for all other nodesCUnmanage resource groups on one node, update the cluster filesets, start cluster services. Wait for thecluster to stabilize and repeat for all other nodes.DBring resource groups (RGs) online on all nodes concurrently, bring RGs offline on one node, update thecluster filesets, bring RGs online, repeat for all other nodes

单选题A network for a two-node cluster has been planned. The network administrator has explained that the networkdoes not support gratuitous ARP. Which of the following steps will ensure that clients are able to connect tothe cluster after a failover takes place?()AImplement heartbeating over IP aliasesBImplement persistent service IP addressesCImplement IPAT aliasing with hardware address takeover (HWAT)DImplement IPAT replacement with hardware address takeover (HWAT)

单选题An administrator has integrated a new application into an existing resource group. An application server withstart and stop scripts was defined and added to the resource group definition. The cluster was thensynchronized. How can the new application be started with minimal downtime?()AThe administrator will need to perform an rg_move operationBThe administrator will need to un-manage and re-manage the resource groupCThe administrator will need to execute the new start script from the command lineDThe new start script will be executed as part of the DARE operation to synchronize the cluster