单选题A customer plans to install ten Microsoft Windows servers, three Linux servers, and five AIX servers, with two Fibre Channel host bus adapters each as part of an IBM DS8700 implementation. What multipathing driver is required to build a redundant solution?()ARDACBMPIOCSSPCDSDDPCM

单选题
A customer plans to install ten Microsoft Windows servers, three Linux servers, and five AIX servers, with two Fibre Channel host bus adapters each as part of an IBM DS8700 implementation. What multipathing driver is required to build a redundant solution?()
A

RDAC

B

MPIO

C

SSPC

D

SDDPCM


参考解析

解析: 暂无解析

相关考题:

A customer plans to install ten Microsoft Windows servers, three Linux servers, and five AIX servers, with two Fibre Channel host bus adapters each as part of an IBM DS8700 implementation.What multipathing driver is required to build a redundant solution?()A.RDACB.MPIOC.SSPCD.SDDPCM

Your organization has an Active Directory Domain Services (AD DS) domain. All servers run Windows Server 2008 R2.You need to deploy Microsoft Application Virtualization (App-V) 4.6 in a stand-alone configuration.Which should you install?()A.Microsoft Application Virtualization DatabaseB.Microsoft Application Virtualization Desktop ClientC.Microsoft System Center Application Virtualization Streaming ServerD.Microsoft System Center Application Virtualization Management Server

A Customer has a functional server deployment solution that uses a combination of disk imaging and application pushing technology. They need to get a working Windows 2003 image for their new servers as soon as possible. What method can achieve this?()A、Install Windows 2003 using the F6 supply Mass Storage Controller optionB、Replace Customer’s deployment solution with Tivoli Provisioning Manager for OS Deployment Director EditionC、Deploy Customer’s existing image and use UXSPi to update IBM specific driversD、Use ServerGuide to install Windows 2003

A customer plans to install ten Microsoft Windows servers, three Linux servers, and five AIX servers, with two Fibre Channel host bus adapters each as part of an IBM DS8700 implementation. What multipathing driver is required to build a redundant solution?()A、RDACB、MPIOC、SSPCD、SDDPCM

Your organization has an Ac tive Directory Domain Services (AD DS) domain. All servers run Windows Server 2008 R2. You need to deploy Microsoft Application Virtualization (App - V) 4.6 in a stand - alone configuration. Which should you install?()A、Microsoft Application Virtualization Data baseB、Microsoft Application Virtualization Desktop ClientC、Microsoft System Center Application Virtualization Streaming ServerD、Microsoft System Center Application Virtualization Management Server

retail company plans to consolidate 180 existing dual processor Xeon servers, all running a web server application on Windows Server 2003. They are planning consolidating to a single x3950 X5 running vSphere.Which of the following should be discussed with this customer? ()A、Is the web content static or dynamic information B、Consider two servers for redundancy and failover C、What is the average CPU utilization of the existing web servers D、Will the servers need a SCSI or Fibre Channel storage solution

An existing IBM customer has some iSeries servers in their environment.  The customer is adding an x366 server with an RSA-II installed for their Microsoft Client/Server applications.  The customer wants to consolidate the storage and centralize the backup of the iSeries and xSeries platforms.  Which of the following will accomplish this?()A、Share the data over the Ethernet LAN.B、Install the IXA Adapter in the iSeries server.C、Install the IXA Adapter in the xSeries server.D、Attach both servers to an IXS switch.

A customer is consolidating their ten rack mount Windows servers into a VMware environment with four servers. The existing servers all have internal disk. The total amount of useable capacity is 5TB which is expected to increase to 10TB over the life of this asset. The customer will want to use the advanced features of VMware like VMotion.The customer is concerned about cost. Which of the following meets the customers needs? ()A、DS3500 with SAS Host Connection B、DS3500 with iSCSI Host Connection C、DS3500 with FC Host Connection D、DS5020

A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700.  They would like to upgrade and plan for 40 TB capacity.  The customer needs to move to a more scalable storage system to include all servers.Which of the following would be most appropriate to ask first?()A、What are the plans for Disaster Recovery? B、What are the plans for data migration? C、Would iSCSI meet your needs? D、How much space is available in the current storage systems?

A customer needs to deploy ten dual processor Xeon servers.  Six servers will be running Linux and Apache, and the other four will be Citrix presentation servers.  The customer’s main concerns are the rack space and the option to have SATA drives.  The maximum memory required is 8GB.  Which of the following options will provide the best price and performance?()A、Ten x306’s with internal SATA drivesB、Five x346’s with internal SATA drives and VMWare ESX ServerC、Five x366’s partitioned into two VMs each with VMWare ESX ServerD、Ten x336’s with internal SATA drives

A customer plans to replace a McData 6140 core director with a Cisco MDS 9506. The storage is based on SVC with three DS5300 back-end storage systems. The storage resources are attached to the 6140 core while all servers are attached to edge switches. Linux, Windows and AIX servers use the SVC. Which of the following is a potential risk associated with this planned migration?()A、thereare no potential risksB、the FCIDs of the servers must be changedC、the SVC must be shut down during the migrationD、changing the FCIDs of storage resources will impact some servers

The customer is consolidating their ten rack mount Windows servers into a VMware environment with four servers. The existing servers all have internal disk. The total amount of useable capacity is 5TB which is expected to increase to 10TB over the life of this asset. The customer will want to use the advanced features of VMware like VMotion. The customer is concerned about cost. Which of the following meets the customers needs?()A、DS3500 with SAS Host ConnectionB、DS3500 withiSCSI Host ConnectionC、DS3500 with FC ConnectionD、DS5020

A retail company plans to consolidate 180 existing dual processor Xeon servers, all running a web server application on Windows Server 2003. They are planning consolidating to a single x3950 X5 running vSphere. Which of the following should be discussed with this customer?()A、Consider two servers for redundancy and failoverB、Web content static or dynamic informationC、Processor utilization of the existing web serversD、SCSI orFibre Channel storage solution

A customer is running a number of non-IBM servers purchased two years ago and has settled on one of the new IBM xSeries servers as a migration path.  From the following options, which is the preferred migration path?()A、Copy the image of the non-IBM servers and copy that image to the IBM servers, then reboot the IBM servers.B、Copy the image from the non-IBM servers with RDM and install them with IBM Director to the new IBM servers. Reboot the IBM servers.C、Install a fresh operating system using ServerGuide, and then install the applications and copy the data from the old servers.D、Install a fresh operating system on the IBM servers and then run ServerGuide on the IBM servers to migrate the applications and data to the IBM servers.

A customer wants to implement a clustered database solution on their existing x445 servers.  A minimum of four nodes must participate in the cluster, and the customer wishes to use open standards.  Which of the following best satisfies their requirements?()A、Novell NetWare Cluster ServicesB、Red Hat Enterprise Linux Cluster SuiteC、Microsoft Windows 2003 Server with MSCSD、Microsoft Windows 2003 Enterprise Edition

A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700. They would like to upgrade and plan for 40 TB capacity. The customer needs to move to a more scalable storage system to include all servers. Which of the following would be most appropriate to ask first?()A、What are Disaster RecoveryplansB、What are plans for datamigrationC、What storage system space isavailableD、DoesiSCSI meet the needs

A Customer has a proprietary server deployment solution that uses a combination of disk imaging and application pushing technology. They need to get a working Windows 2003 image for their new servers as soon as possible for deployment with their provisioning system. Which of the following methods can achieve this?()A、UseServerGuide to install Windows 2003rchase PowerVM Standard Edition for the entire systemB、Install Windows 2003 using the F6 supply Mass Storage Controller optionC、Replace Customer’s deployment solution with Tivoli Provisioning Manager for OS Deployment Director EditionD、Deploy Customer’s existing image and useUXSPi to update IBM specific drivers

Your network contains a Web-based application that runs on Windows Server 2003. You plan to  migrate the Web-based application to Windows Server 2008 R2. You need to recommend a server  configuration to support the Web-based application. The server configuration must meet the following  requirements:   èEnsure that the application is available to all users if a single server?fails èSupport the installation of .NET applications èMinimize software costs  What should you recommend?() A、Install the Server Core installation of Windows Server 2008 R2 Standard on two servers. Configure the servers in a Network Load Balancing cluster.B、Install the full installation of Windows Server 2008 R2 Web on two servers. Configure the servers in a Network Load Balancing cluster.C、Install the full installation of Windows Server 2008 R2 Enterprise on two servers. Configure the servers in a failover cluster.D、Install the full installation of Windows Server 2008 R2 Datacenter on two servers. Configure the servers in a failover cluster.

You run Windows Defender on your computer and receive the following warning message:  "Windows Defender Definitions havent been updated."  You need to ensure that Windows Defender definition files are updated.  What should you do?()A、Restart the Windows Defender service.B、Repair the Microsoft Location Finder program.C、Download and install the appropriate files from Microsoft Windows Update.D、Download and install the latest Windows Defender application from the Microsoft Web site.

Your company plans to deploy eight file servers that run Windows Server 2008 R2. All file servers will connect to Ethernet switches.  You need to plan a data storage solution that meets the followingrequirements:   èAllocates storage to the servers as needed èUtilizes the existing network infrastructure  èMaximizes performance  èMaximizes fault tolerance   Which actions should you include in your plan?()A、Install Windows Server 2008 R2 Datacenter on each server. Deploy the servers in a failover cluster. deploy an iSCSI storage area network (SAN).B、Install Windows Server 2008 R2 Standard on each server. Deploy the servers in a Network Load balancing (NLB) cluster. Implement RAID?5 on each server.C、Install Windows Server 2008 R2 Enterprise on each server. Deploy the servers in a failover cluster. deploy a Fibre Channel (FC) storage area network (SAN).D、Install Windows Server 2008 R2 Enterprise on each server. Deploy the servers in a Network Load balancing (NLB) cluster. Map a network drive on each server to an external storage array.

Your company purchases 15 new 64-bit servers as follows: èFive of the servers have a single processor.    èFive of the servers have a single dual core processor. èFive of the servers have two quad core processors.   You plan to deploy Windows Server 2008 R2 on the new servers by using Windows Deployment Services (WDS).  You need to recommend a WDS install image strategy that meets the following requirements: Minimizes the number of install images   Supports the deployment of Windows Server 2008 R2 What should you recommend?()A、one install image file that contains three install imagesB、one install image file that contains a single install imageC、two install image files that each contain a single install imageD、three install image files that each contain a single install image

Your computer runs Microsoft Windows Vista Home Basic edition.  You need to record television programs by using Microsoft Windows Media Center. You add a compatible TV tuner.  What should you do next?()A、Configure Windows Media Center to recognize the tuner.B、Install Windows Media Center.C、Upgrade to Microsoft Windows Vista Home Premium edition.D、Run a Microsoft Windows Update scan against the Microsoft Update servers.

A Microsoft Exchange mobile messaging solution uses Microsoft Windows Mobile 5.0 with  Microsoft Messaging and Security Feature Pack. You deploy the solution by using front-end and back-end servers. Microsoft Exchange Server 2003 Service Pack 2 is installed on the front-end server.   You need to use the remote wipe feature.   What should you do?()A、Install Microsoft Windows Server 2003 Service Pack 2 on all domain controllers. B、Install Microsoft Exchange Server 2003 Service Pack 2 on the back-end server. C、Install Microsoft Exchange Server ActiveSync Web Administration Tool on the front-end server.D、Install Microsoft Exchange Server ActiveSync Web Administration Tool on the back-end server.Reset Instructions Calculator.

You need to recommend a Windows Server 2008 R2 server configuration that meets the following  requirements:   èSupports the installation of Microsoft SQL Server 2008   èProvides redundancy for SQL services if a single server fails What should you recommend?() A、Install a Server Core installation of Windows Server 2008 R2 Enterprise on two servers. Configure the servers in a failover cluster.B、Install a full installation of Windows Server 2008 R2 Standard on two servers. Configure Network Load Balancing on the two servers.C、Install a full installation of Windows Server 2008 R2 Enterprise on two servers. Configure Network Load Balancing on the two servers.D、Install a full installation of Windows Server 2008 R2 Enterprise on two servers. Configure the servers in a failover cluster.

Your network consists of a single Active Directory domain. All domain controllers run Windows Server 2008 R2. All servers run Windows Server 2008 R2. All client computers run Windows 7.   You need to generate a monthly report on the status of software updates for the client computers.  Your solution must meet the following requirements:   èDisplay all of the operating system updates that installed successfully  èDisplay all of the Microsoft application updates that installed successfully  èDisplay all of the operating system updates that failed to install   èDisplay all of the Microsoft application updates that failed to install èMinimize administrative effort  èMinimize costs What should you do?()A、Install Microsoft System Center Essentials (Essentials) 2007. Deploy management agents on all client  computers.B、Install Microsoft System Center Configuration Manager (SysMgr) 2007. Deploy management agents  on all client computers.C、Install Windows Server Update Services(WSUS)3.0SP2.Configure Windows Update byusing a Group Policy object (GPO).D、Deploy Microsoft Baseline Security Analyzer (MBSA) 2.1 on the client computers. Run MBSA on each client computer, and save the report to a shared folder on the network.

单选题retail company plans to consolidate 180 existing dual processor Xeon servers, all running a web server application on Windows Server 2003. They are planning consolidating to a single x3950 X5 running vSphere.Which of the following should be discussed with this customer? ()AIs the web content static or dynamic information BConsider two servers for redundancy and failover CWhat is the average CPU utilization of the existing web servers DWill the servers need a SCSI or Fibre Channel storage solution

单选题A Customer has a proprietary server deployment solution that uses a combination of disk imaging and application pushing technology. They need to get a working Windows 2003 image for their new servers as soon as possible for deployment with their provisioning system. Which of the following methods can achieve this?()AUseServerGuide to install Windows 2003rchase PowerVM Standard Edition for the entire systemBInstall Windows 2003 using the F6 supply Mass Storage Controller optionCReplace Customer’s deployment solution with Tivoli Provisioning Manager for OS Deployment Director EditionDDeploy Customer’s existing image and useUXSPi to update IBM specific drivers

单选题A Customer has a functional server deployment solution that uses a combination of disk imaging and application pushing technology. They need to get a working Windows 2003 image for their new servers as soon as possible. What method can achieve this?()AInstall Windows 2003 using the F6 supply Mass Storage Controller optionBReplace Customer’s deployment solution with Tivoli Provisioning Manager for OS Deployment Director EditionCDeploy Customer’s existing image and use UXSPi to update IBM specific driversDUse ServerGuide to install Windows 2003