In the PDM, common constraints include:A.Start-to-startB.Finish-to-startC.Finish-to-finishD.B and C onlyE.A, B, and C.

PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity. A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

PDM includes four types of dependencies or precedence relation ships:(73)The completion of the successor activity depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

PDM includes four types of dependencies or precedence relationships.( ),the initiation of the successor activity,depends upon the initiation ofthe predecessor activity. A.Start-to-Start B.Finish-to-Finish C.Start-to-Finish D.Finish-to—Start

PDM includes four types of dependencies or precedence relationships…(73),the initiation of the successor activity,depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

PDM includes four types of dependencies or precedence relationships: ...(18). The completion of the successor activity depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

● Precedence Diagramming Method (PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called __(75)__.(75)A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ). A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish

“一旦小玲写完了实验代码并且运行成功,她就不会延迟提交论文并且周一会给老师看。”以下表示正确的是:A.finish(小玲,代码)∧work(代码) → delay_submit(小玲,论文) ∨ give(小玲,论文,teacher(小玲))B.finish(小玲,代码)∧work(代码) ∧ ¬delay_submit(小玲,论文) ∧ give(小玲,论文,teacher(小玲))C.finish(小玲,代码)∧ work(代码) ∧ ¬delay_submit(小玲,论文) ∧ give(论文,teacher(小玲))D.finish(小玲,代码)∧ work(代码) → ¬delay_submit(小玲,论文) ∧ give(小玲,论文,teacher(小玲))