It _________________ me two days to finish the report. A、takesB、spendsC、costsD、pays

It _________________ me two days to finish the report.

A、takes

B、spends

C、costs

D、pays


相关考题:

In the PDM, common constraints include:A.Start-to-startB.Finish-to-startC.Finish-to-finishD.B and C onlyE.A, B, and C.

150 In the PDM, common constraints include:A. Start-to-startB. Finish-to-startC. Finish-to-finishD. B and C onlyE. A, B, and C.

32 In the PDM, common constraints include:A. Start-to-startB. Finish-to-startC. Finish-to-finishD. B and C onlyE. A, B, and C

PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity. A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

PDM includes four types of dependencies or precedence relation ships:(73)The completion of the successor activity depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

PDM includes four types of dependencies or precedence relationships.( ),the initiation of the successor activity,depends upon the initiation ofthe predecessor activity. A.Start-to-Start B.Finish-to-Finish C.Start-to-Finish D.Finish-to—Start

PDM includes four types of dependencies or precedence relationships…(73),the initiation of the successor activity,depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

PDM includes four types of dependencies or precedence relationships: ...(18). The completion of the successor activity depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

● Precedence Diagramming Method (PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called __(75)__.(75)A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ). A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish