Which of the following technologies was created to reduce cost, increase cable length, and uses 3.3v across the line?() A. Wide-Ultra2 SCSI-3B. High-Voltage DifferentialC. Low-Voltage DifferentialD. Fibre Channel

Which of the following technologies was created to reduce cost, increase cable length, and uses 3.3v across the line?()

A. Wide-Ultra2 SCSI-3

B. High-Voltage Differential

C. Low-Voltage Differential

D. Fibre Channel


相关考题:

In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.A.Increase, decrease.B.Increase, increaseC.Increase, increase or decrease.D.Decrease, decrease.E.Decrease, increase.

Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.A . Increase, increase.B . Increase, decrease.C . Decrease, decrease.D . Decrease, increase.E . Remain the same, return to customer.

185 In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.A. Increase, decrease.B. Increase, increaseC. Increase, increase or decrease.D. Decrease, decrease.E. Decrease, increase

6 Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.A. Increase, increase.B. Increase, decrease.C. Decrease, decrease.D. Decrease, increase.E. Remain the same, return to customer

67 In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.A. Increase, decrease.B. Increase, increaseC. Increase, increase or decrease.D. Decrease, decrease.E. Decrease, increase

88 Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.A. Increase, increase.B. Increase, decrease.C. Decrease, decrease.D. Decrease, increase.E. Remain the same, return to customer

You’re going to have a quiz ( )by another two in the ( )month. A. followed,followedB. followed,followingC. following,followedD. following,following

直线命令“LINE”中的“C”选项表示()。 A.闭合CLOSEB.继续CONTINUEC.创建CREATED.粘连CLING

Giventhefollowingcodefragment:1)Stringstr=null;2)if((str!=null)(str.length()10)){3)System.out.println(morethan10);4)}5)elseif((str!=null)(str.length()5)){6)System.out.println(lessthan5);7)}8)else{System.out.println(end);}Whichlinewillcauseerror?()A.line1B.line2C.line5D.line8

The relative pronoun "which" in the last paragraph (Line 6) refers to (  ).A.expertsB.periodsC.theoriesD.issues