单选题A new administrator is performing fallover testing on a two-node cluster and is concerned that the cascading resource group belonging to Node ’A’ did not reintegrate properly after the cluster was restarted on Node ’A’. A stable cluster is reported by clstat,and clRGinfo reports the resource group online on Node ’B’.  What type of configuration would cause this type of behavior?()A The resource group DNP has been configured.B The resource group option CWOF has been enabled.C The resource group option Inactive Takeover is set.D A resource group fallback timer has been configured.

单选题
A new administrator is performing fallover testing on a two-node cluster and is concerned that the cascading resource group belonging to Node ’A’ did not reintegrate properly after the cluster was restarted on Node ’A’. A stable cluster is reported by clstat,and clRGinfo reports the resource group online on Node ’B’.  What type of configuration would cause this type of behavior?()
A

 The resource group DNP has been configured.

B

 The resource group option CWOF has been enabled.

C

 The resource group option Inactive Takeover is set.

D

 A resource group fallback timer has been configured.


参考解析

解析: 暂无解析

相关考题:

______(increase),new technology is making it easier for us to find alternative methods of testing.

Which three tasks can be performed using a duplicate database?() A. Testing the backup and recovery proceduresB. Testing the upgrade of an Oracle database to a new releaseC. Testing the effect of an application changes on database performanceD. Continuously updating archive log files from the target database to support failover

You are using a recovery catalog to maintain Recovery Manager (RMAN) backup information for yourproduction database. You have registered your production database and are performing regular backups.Because of a new requirement you have added a few new tablespaces to your production database and youwant them to be included in backups.Identify two options for completing this task. ()(Choose two.)A. Reregistering the target database in recovery catalogB. Transporting the new tablespaces to the recovery catalog databaseC. Syncronizing the recovery catalog with the target database control fileD. Performing a fresh backup of the target database to include the new data files in the catalog database

Which three tasks can be performed using a duplicate database? ()(Choose three.) A. Testing the backup and recovery proceduresB. Testing the upgrade of an Oracle database to a new releaseC. Testing the effect of an application changes on database performanceD. Continuously updating archive log files from the target database to support failover

You are performing two sums: the first is a sum of two scalar variables and the second is a matrix sum of a pair of two- dimensional arrays-size 1000 by 1000.What speedup is achieved when the calculations are performed on size 1000 processors?A.50B.100C.999D.none of the above

12. About_______ of the workers in the factory were born in the __________.A. two- thirds;1970B. two- thirds ; 1970sC. two-third ; 1970D. two-third ; 1970s

Which three tasks can be performed using a duplicate database?()A、Testing the backup and recovery proceduresB、Testing the upgrade of an Oracle database to a new releaseC、Testing the effect of an application changes on database performanceD、Continuously updating archive log files from the target database to support failover

You are designing a strategy to upgrade the DHCP servers after the new Active Directory structure is in place.  Who can authorize the DHCP servers?()A、 Chief information officerB、 IT support staff in BostonC、 IT support staff in New YorkD、 Network administrator in ChicagoE、 Network administrator in New York

What is needed to verify that a newly implemented security solution is performing as expected? ()A、a detailed physical and logical topologyB、a cost analysis of the implemented solution C、detailed logs from the AAA and SNMP serversD、results from audit testing of the implemented solution

An administrator is testing setting the IP address on a Linux server from command line. Which of the following commands is used to set the default gateway for the server?()A、routeB、tracerouteC、ipconfigD、nmap

The administrator has just installed a new memory module into the server. Now, the server is not showing the new memory. Which of the following should the administrator perform FIRST?()A、System rebootB、Reseat the memoryC、Install the latest firmwareD、Install the latest driver

A cluster administrator is performing fallover testing during a scheduled system outage. Node ’A’  Was forced down and eventually rebooted. When Node ’A’ reintegrates into the cluster, the resource group state is offline. No errors are found in reviewing the hacmp.out file.  What could have been done to ensure the resource group was acquired when cluster processing was restarted on Node ’A’?()A、 Nothing,HACMP does not require them automatically.B、 Force the remaining nodes down,then reintegrate them all.C、 Select reacquire resources after forced down on start menu.D、 Create a setting timer to bring the resource group online.

A new administrator is performing fallover testing on a two-node cluster and is concerned that the cascading resource group belonging to Node ’A’ did not reintegrate properly after the cluster was restarted on Node ’A’. A stable cluster is reported by clstat,and clRGinfo reports the resource group online on Node ’B’.  What type of configuration would cause this type of behavior?()  A、 The resource group DNP has been configured.B、 The resource group option CWOF has been enabled.C、 The resource group option Inactive Takeover is set.D、 A resource group fallback timer has been configured.

During the process of fallover testing, a client/server database needs to be tested. On the AIX Server, start/stop/cleanup scripts and server application functionality have been tested.  Before moving onto the next step of fallover testing,what action must be completed?()A、 Run who -a and validate that client connections are restored.B、 Verify that the client side application is functioning properly.C、 Check hacmp.out log file to validate that the application server started.D、 Verify that the application will successfully stop and restart on the fallover node.

During cluster fallover testing,the administrator determines that additional work is required to stop existing test applications on the standby node,prior to starting the production applications on the surviving node.  To manage this type of requirement,which step should be performed first?()  A、 Create a custom pre/post event.B、 Add a custom user defined event.C、 Define custom error notification.D、 Modify the test application server.

An administrator has integrated a new application into an existing resource group. An application server withstart and stop scripts was defined and added to the resource group definition. The cluster was thensynchronized. How can the new application be started with minimal downtime?()A、The administrator will need to perform an rg_move operationB、The administrator will need to un-manage and re-manage the resource groupC、The administrator will need to execute the new start script from the command lineD、The new start script will be executed as part of the DARE operation to synchronize the cluster

During an internal IT organization planning session, it is decided that a new cluster node would  Enhance the performance of a distributed corporate application. Planning details have been assigned to the administrator. System outages are limited to one weekend per month; therefore, availability will be a key issue in the planning process.  How much cluster downtime will need to be allocated for adding a new node?()  A、 None,everything can be done with the cluster active.B、 Minimal downtime will be required to import the volume groups.C、 Several hours are required for testing before final synchronization.D、 Minimal downtime will be required to connect and test the serial network.

Which three tasks can be performed using a duplicate database? ()(Choose three.)A、Testing the backup and recovery proceduresB、Testing the upgrade of an Oracle database to a new releaseC、Testing the effect of an application changes on database performanceD、Continuously updating archive log files from the target database to support failover

You are using a recovery catalog to maintain Recovery Manager (RMAN) backup information for yourproduction database. You have registered your production database and are performing regular backups. Because of a new requirement you have added a few new tablespaces to your production database and youwant them to be included in backups.Identify two options for completing this task. ()(Choose two.)A、Reregistering the target database in recovery catalogB、Transporting the new tablespaces to the recovery catalog databaseC、Syncronizing the recovery catalog with the target database control fileD、Performing a fresh backup of the target database to include the new data files in the catalog database

单选题During the process of fallover testing, a client/server database needs to be tested. On the AIX Server, start/stop/cleanup scripts and server application functionality have been tested.  Before moving onto the next step of fallover testing,what action must be completed?()A Run who -a and validate that client connections are restored.B Verify that the client side application is functioning properly.C Check hacmp.out log file to validate that the application server started.D Verify that the application will successfully stop and restart on the fallover node.

单选题A cluster administrator is performing fallover testing during a scheduled system outage. Node ’A’  Was forced down and eventually rebooted. When Node ’A’ reintegrates into the cluster, the resource group state is offline. No errors are found in reviewing the hacmp.out file.  What could have been done to ensure the resource group was acquired when cluster processing was restarted on Node ’A’?()A Nothing,HACMP does not require them automatically.B Force the remaining nodes down,then reintegrate them all.C Select reacquire resources after forced down on start menu.D Create a setting timer to bring the resource group online.

单选题During cluster fallover testing,the administrator determines that additional work is required to stop existing test applications on the standby node,prior to starting the production applications on the surviving node.  To manage this type of requirement,which step should be performed first?()A Create a custom pre/post event.B Add a custom user defined event.C Define custom error notification.D Modify the test application server.

单选题An administrator has integrated a new application into an existing resource group. An application server withstart and stop scripts was defined and added to the resource group definition. The cluster was thensynchronized. How can the new application be started with minimal downtime?()AThe administrator will need to perform an rg_move operationBThe administrator will need to un-manage and re-manage the resource groupCThe administrator will need to execute the new start script from the command lineDThe new start script will be executed as part of the DARE operation to synchronize the cluster

单选题What is needed to verify that a newly implemented security solution is performing as expected? ()Aa detailed physical and logical topologyBa cost analysis of the implemented solution Cdetailed logs from the AAA and SNMP serversDresults from audit testing of the implemented solution

单选题You are designing a strategy to upgrade the DHCP servers after the new Active Directory structure is in place.  Who can authorize the DHCP servers?()A Chief information officerB IT support staff in BostonC IT support staff in New YorkD Network administrator in ChicagoE Network administrator in New York

单选题An administrator has an existing HMC and POWER6 570 connected to a network switch. The administrator is planning to install two POWER6 570s with a dedicated HMC. Which infrastructure is required for the new HMC?()AAn additional switch for the new HMCBAsynchronous adapters on the new HMCCThe two 570 servers are directly connected to the new HMCDOne 570 is directly connected to the new HMC and the other is directly connected to the existing HMC

单选题You are designing a strategy to upgrade the DHCP servers after the new Active Directory structure is in place. Who can authorize the DHCP servers?()AChief information officerBIT support staff in BostonCIT support staff in New YorkDNetwork administrator in ChicagoENetwork administrator in New York