单选题A wooden float placed between a ship and a dock to prevent damage to both is called a().AcamelBdolphinCrat guardDwedge
单选题
A wooden float placed between a ship and a dock to prevent damage to both is called a().
A
camel
B
dolphin
C
rat guard
D
wedge
参考解析
解析:
暂无解析
相关考题:
The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:A.SlackB.Free float.C.Restricted float.D.Level float.E.Lag
22 The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:A. SlackB. Free float.C. Restricted float.D. Level float.E. Lag
Although a ship usually has repair in a shipyard, ________ is also necessaryA.the general repair on boardB.the voyage repairC.the annual repairD.the dock repair
A spring line leads ______.A.fore and aft from the ship’s sideB.to the dock at a right angle to the vesselC.through the bull nose or chock at the bowD.through the chock at the stern
A wooden float placed between a ship and a dock to prevent damage to both is called a ______.A.camelB.dolphinC.rat guardD.wedge
______ is not an item of the communication between the ship and shore.A.agreed procedure to STOP cargo operationsB.Personnel responsible for terminal cargo operationsC.agreed procedure for draught checkingD.agreement between the ship's Master and the terminal representative
On a ship,a door that is required to be marked KEEP CLOSED is designed to ______.A.prevent the passage of flammable gasesB.prevent the passage of poisonous vaporsC.delay the spread of heat and flamesD.maintain watertight integrity
A deck beam does NOT ______.A.act as a beam to support vertical deck loadsB.lessen the longitudinal stiffness of the vesselC.act as a tie to keep the sides of the ship in placeD.act as a web to prevent plate wrinkling due to twisting action on the vessel
Cribbing is ______.A.wooden blocks or dunnage placed between a deck load and the deckB.the chains and shackles used to secure a deck cargoC.a crate in which a deck cargo is packagedD.cardboard separation pieces placed between deck loads to prevent chafing
class super { public float getNum() {return 3.0f;} } public class Sub extends Super { } Which method, placed at line 6, will cause a compiler error?()A、 Public float getNum() {return 4.0f; }B、 Public void getNum (){}C、 Public void getNum (double d){}D、 Public double getNum (float d) {retrun 4.0f; }
单选题A carling is used aboard ship().Aas a connecting strap between the butted ends of platingBto stiffen areas under points of great stress between beamsCto prevent the anchor from fouling when the brake is releasedDto provide an extra heavy fitting in a heavy lift cargo rig
单选题To prevent a wooden hull from leaking you caulk it().Aafter drydocking,while the hull is moistBafter drydocking,and the hull has driedCafloat,where it is leakingDafloat,in all accessible areas
单选题The officer in charge of the engineering watch shall ensure that all machinery involved with the maneuvering of the ship can immediately be placed in the () of operation when notified that the ship is in congested waters.Amanual modeBautomatic modeCremote modeDfollow-up mode
单选题The emergency bilge suction or bilge injection valve is used to prevent () of the ship.AproceedingBoverloadingCcollisionDflooding
单选题When a ship is fully loaded, it needs to prevent the main engine to be().While a ship is fully empty, it needs to prevent the main engine to be().Aoverspeed;overloadBoverload;overspeedCover mechanical load;over thermal loadDover torque;overspeed
单选题When ship in the dock repairing, engine department should emphasize on the inspection of()Asea valve chest, sect valve, thrusterBbilge motherboard, steering and the shaft systemCsea water systemDfresh water system
单选题In a river subject to tidal currents,the best time to dock a ship without the assistance of tugs is().Aat high waterBwhen there is a following currentCat slack waterDat flood
单选题You are docking a vessel starboard side to with the assistance of two tugs.You are attempting to hold the vessel off by operating both tugs at right angles to the vessel and at full power.You must ensure that().Asteerageway is not taken offBthe bow doesn't close the dock firstCthe bow closes the dock firstDthe ship has no headway at the time
单选题What is placed on the underside of an inflatable liferaft to help prevent it from being skidded by the wind or overturned? ()ABallast bagsBA keelCStrikesDSea anchor
单选题Vessel shall be placed at the()of the Charterers in such dock or at such berth or place as the Charterers may direct.AdisposalBcontrolCoperationDoption
单选题A wooden plug fitted tightly in the vent of a damaged tank may prevent the tank from().Afilling completelyBdeveloping free surfaceCdeveloping free surface momentDcollapsing
单选题Cribbing is().Awooden blocks or dunnage placed between a deck load and the deckBthe chains and shackles used to secure a deck cargoCa crate in which a deck cargo is packagedDcardboard separation pieces placed between deck loads to prevent chafing
单选题A carling is used aboard ship().Aas a connecting strap between the butted ends of platingBto stiffen areas under points of great stress between beamsCto prevent the anchor from fouling when the brake is releasedDto provide an extra heavy fitting in a lift cargo released
单选题The wooden plug inserted in the vent of a damaged tank of a ship should be removed in case it is decided to().Apump from the damaged tankBfight a fireCabandon the rigDuse the crossover system
单选题Which of the following precautions should always be carried out in dry dock?()ALiquids should never be transferred between tanks without consulting the dock masterBIf sea valves have been disassembled, all bonnets must be checked for leakage when the ship is re-floatedCBefore re-floating, all sea chest strainers should be verified as having been replacedDAll of the above
单选题When checking a mooring line,you should().Aensure the bight is not fouled between the ship and the dock by taking up slackBpay out slack smartly and keep free for runningCsecure more turns to hold the line against any strain,then clear the areaDsurge the line so that it maintains a strain without parting